It has been a little over 6 months since we broke ground in our lot of dirt; we now have framework, wiring, plumbing and some walls!
Here is a quick timeline of what our construction crew has been up to the last few months:
In January the construction crew began mapping out foundations.
March, all underground sewage pipes were installed. Street concrete, creating the turning lane and entrance to the branch space was poured.
By April, our crew completed the foundation! From framing to pouring the concrete. Now to wait for it to dry completely. Pavement was also poured on the turning lane, completing the entrance to the new location!
May, now that the concrete is dry, our construction crew started on the framework and outer walls. Our branch is starting to look like an actual building! The parking lot was also paved, so you now have a place to park when you come see us!
June, we are truly starting to look like a Credit Union now! There is dry wall on the outside, plumbing, electrical wiring and AC installation. And we have glass doors!
Come check back on our progress next month!